Retail
Residential
Community
Contact
Building Progress
April 11th, 2008
Six weeks ahead of schedule!! Bamboo floors installed
in seven units, bathrooms completed in six units, kitchens installed
in five units, carpeting installed in one unit. Doors hung in six
units. Two units completely trimmed out. Washer dryers in two units.
All eleven units walls and ceilings painted. New main entrance
starting in ten days!
![]() Kitchen from living room apartment 209 (typical of all kitchens) |
![]() Fireplace installed in apartment 207 (will also be in 204 and 206) |
![]() Bedroom - carpet, doors and trim 209 (typical of all units) |
![]() Washer and dryer (typical) |
![]() On-demand hot water heater (typical) |
![]() Closer view kitchen - apartment 209 |
February 25th, 2008
![]() Subway tile going in the bathrooms with Marmoluem flooring . |
![]() Bamboo flooring going in over natural cork (the darker material on the left). The cork provides an extra level of quiet and is normally used only in very high end homes. |
February 13th, 2008
![]() Unit 207 - drywall finishers applying the final coat on the ceiling in the living room. |
![]() Unit 203 - project manager inspecting drywall work in preparation for approving painting. |
![]() Unit 209 - painters applying second coat of Pittsburgh Paint Pure Performance Accolade in the living room. |
January 28th, 2008
Both walls between units and those in common with hallways from the floor
to the underside of the roof have Homasote
440 with Nu-Wool
Wall Seal System for sound deadening. Also the floor has
2" of solid wood, then a layer
of Homasote 440, 5/8" underlayment, cork to lessen the sounds of walking
and then the finish flooring.
![]() Nu-Wool Wall Seal being installed for sound deadening. |
![]() Finished walls ready for drywall. |
![]() A cross section close-up: each apartment has its own 2 x 4 framed wall with Homasote 440 between the two separate walls. |
January 22nd, 2008
The bedroom skylights being installed on the roof. Mechanicals run in the ceiling of the main hallway routing to the mechanical room: black pipe are gas, orange are sprinkler lines, blue are water supply lines.
![]() |
![]() |
December 13th, 2007
Country Arbors Nursery owner Joe Cultra and a helper move a yew already installed in the all weather planter to a platform. The platforms were constructed using 4 x 4s made from recycled automobiles and planking made from recovered wood scrapes surrounded by a stable polymer. The 4 x 4s are 4 feet long to distribute the weight across several roof rafters. The plantings were also placed to be over walls and or trusses.
![]() |
December 9th, 2007
Air jet whirlpools being roughed-in and drywall being hung.
![]() |
![]() |
December 7th, 2007
New windows being installed.
![]() |
November 16th, 2007
Framing well underway.
![]() |
October 7th, 2007
In the midst of demolition. Note the separate piles of demolition materials being separated for recycling.
Out of 280 cubic yards of demolition, over a third (100 cubic yards) was saved from the land fill by being recycled.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
August 2007
What it looked like when we purchased the building.
![]() |
![]() |
![]() |
![]() |





































